Vacation Home 3 – Siding, Soffits and Fascia

By East Silent Resort / March 2, 2014 / Comments Off on Vacation Home 3 – Siding, Soffits and Fascia

  The exterior of the new vacation home is really taking shape. As you can see from these 2/23/2014 photos, the siding is partially completed, the shingles are on, and the soffit and fascia are finished! It’s amazing what can be done with a couple days of nice weather. Spring is just around the corner. […]

Read More

Vacation Home 3 – Lower Level Framing and Insulation

By East Silent Resort / February 27, 2014 / Comments Off on Vacation Home 3 – Lower Level Framing and Insulation

We have some catching up to do! These photos are from Feb. 1st. As you can see, the lower level has been framed out and insulated. Compared to Maplewood and Itasca (the first vacation homes), this lakeside lake home offers a walk-out, lower level. The lower level features 2 bedrooms and 2 bathrooms which can […]

Read More

Vacation Home 3 – Interior Framing and Insulating

By East Silent Resort / February 2, 2014 / Comments Off on Vacation Home 3 – Interior Framing and Insulating

With such cold temperatures in Minnesota this winter, the builders are glad to be working on the interior of the new vacation home. These images are from Jan. 24th. They are working on all interior framing and will be spray foaming insulation in the next several days. We are very excited about the new layout. […]

Read More

Vacation Home 3 – Exterior Framing and Sheathing

By East Silent Resort / December 29, 2013 / Comments Off on Vacation Home 3 – Exterior Framing and Sheathing

It was a beautiful day in Otter Tail Lakes Country yesterday. Mild temps allowed us to spend the day hiking and sledding. Today is much colder (-8). We also took a few minutes to check out the progress on the latest Vacation Home (#3). The exterior framing and sheathing is nearly complete. We are a […]

Read More

Vacation Home 3 – Basement Walls and Floor

By East Silent Resort / December 2, 2013 / Comments Off on Vacation Home 3 – Basement Walls and Floor

The lower level is really taking shape. The walls are set and back filling is complete. These images were taken on November 27th, 2013. The bitter cold didn’t stop us from getting the basement floor poured. I suspect you’ll see floor trusses in our next set up photos!

Read More

Vacation Home 3: Walkout Level Takes Shape

By East Silent Resort / December 2, 2013 / Comments Off on Vacation Home 3: Walkout Level Takes Shape

As you can see, we are making progress on the newest vacation home. These images are from November 9th, 2013. Fortunately, we’ve experienced a relatively mild fall to date which has allowed us to make excellent progress.

Read More